Using MIKE URBAN+ (now MIKE+) for priority reconstruction development
The project—commissioned in December 2012 based on Olomouc’s city development plan and slated to continue into year 2030—comprised three phases covering the city’s water management conditions. In laying the foundation to start off the development, our team elaborated an update of the urban drainage master plan, produced a new water supply master plan and processed a drainage area study. These components were connected into the next fourth phase, that is, the reconstruction plan of future developments. This reconstruction plan evaluated the necessity of water infrastructure repairs and assessed the technical and economic aspects of developments in the pipeline.
The team developed models for each phase of the project using MIKE URBAN (now MIKE+), our reconstruction software tool, with the extent of coverage as follows:
- water supply master plan – 328 km of network
- urban drainage master plan – 310 km of network
- drainage area study – 63 km of streams and channels